| Prty |
Title/Description |
Start |
Finish |
Comments/Progress |
Allocated |
Project Mgr |
Budget |
| 1 |
Wiring throughout boat |
01/10/08 |
|
Complete shipside wiring and new instrumentation. (Batt monitors, Tank, Gas) |
|
DEG |
£300 |
| |
|
|
|
Tidy up and completion of all wiring |
|
|
|
| |
|
|
|
DC charger for the Hand Held Radio |
IJ |
|
|
| |
|
|
|
Look at condition of Hand Held Radio |
IJ |
|
|
| 1 |
Main electric panel |
12/11/07 |
|
Complete with any mods., replace temporary panel |
|
|
|
| 1 |
Flourescent lights |
12/11/07 |
|
Fit red LED units in deckhouse. |
|
|
£80 |
| 1 |
No.2 depth / Helm Instruments |
12/11/07 |
|
Not working - link to Helm display defective |
|
|
|
| 1 |
Repair and refit heater |
12/11/07 |
|
Wiring needs sorting. |
NCB |
|
|
| 1 |
Prop shaft and bearing |
12/11/07 |
|
Check out security, alignment etc. after period of use. |
NCB/DEG |
|
|
| 1 |
Varnish and Tidy up topsides |
29/11/09 |
|
Varnish topsides to agreed specification & make repairs as necessary |
LOTS |
TFS |
£300 |
| 1 |
Paint deck & topsides |
29/11/09 |
|
Paint topsides and deck - as instructed by TFS |
LOTS |
TFS |
£200 |
| 1 |
Chain Hook |
29/11/09 |
|
Purchase and install a chain hook to allow chain to be laid off the deck hatch |
|
TFS |
£50 |
| 1 |
Install Tent Arrangement |
29/11/09 |
|
Install tent arrangement to protect boat during varnishing |
|
TFS |
£200 |
| 1 |
New fridge |
|
|
Make new fridge/freezer under portside bunk |
TFS |
|
£1,000 |
| |
|
|
|
|
|
|
|
| 2 |
Liferaft mounts |
12/11/08 |
|
DEG manufactured. To be fitted |
|
DEG |
£50 |
| 2 |
Spinnaker Pole locking pin |
12/11/08 |
|
Tends to jam (bent). Remove and refit. |
|
DEG |
£50 |
| 2 |
Midship fairleads |
01/08/08 |
|
Devise anti-snag arrangement. In hand |
DEG |
|
|
| 2 |
Boom Vang |
12/11/07 |
|
Suggest 3 part cascade 3:3:6. 6:1 aquired More blocks needed |
DEG/TFS |
|
£60 |
| 2 |
Stanchion bases |
12/11/07 |
|
Continue to fit wooden base blocks - and sort out leaks |
JT/CG |
|
£50 |
| 2 |
Masthead topping lift arrangement |
01/10/08 |
|
Re-engineer to avoid chafe? Main halyard arrangement, or lower gooseneck |
DEG |
|
|
| 2 |
Damage to deckhouse (Pindar) |
12/11/07 |
|
Fit new corner piece. |
AB |
|
|
| |
|
|
|
|
|
|
|
| 3 |
Stem |
12/11/07 |
|
Needs fairing: looks terrible! - leave for next time out of water |
|
|
|
| 3 |
Reposition P/S lights |
07/10/08 |
|
Vunerable to damage/loss! Fit guards? |
|
DEG |
|
| 3 |
Survey Deck and counter |
01/10/08 |
|
In order to decide what we need to do, if anything? |
DEG/TFS |
|
|
| 3 |
Library Shelf fiddles |
28/11/09 |
|
Need to be done |
AB |
|
|
| 3 |
Lazyjack system on Main |
10/06/08 |
|
Try out to facilitate sail handling - requires tuning |
TFS |
|
|
| 3 |
Tool and spares storage |
01/06/08 |
|
Toolbox back aboard: add other necessary items. Some already missing! |
|
TFS |
£200 |
| 3 |
Weight loss programme |
04/04/08 |
|
Destore junk carried on board for years! 7 tons above design weight & 28cm low aft! |
|
|
|
| 3 |
Boom crutch |
12/11/07 |
|
Check security of mountings. Consider alternative arrangements. |
DEG/TFS |
|
|
| 3 |
Check out rudder when next slipped |
12/11/07 |
|
Look for cracks. Check anodes. |
|
|
|
| 3 |
Lifeline gates |
12/11/07 |
|
Fitted in wrong position: discuss! - Survey and decide on required action |
JT/CG |
DEG/TS |
£50 |
| 3 |
Galley refurbishment & storage - Crash Bar |
01/10/08 |
|
Improve to retain items and keep sauces off charts; see chart table fiddles! |
|
|
£30 |
| 3 |
Deck Leaks |
12/11/07 |
never! |
round mast, port quarter berth, etc etc Windlass cover |
|
|
|
| 3 |
Forehatch leaks |
12/11/07 |
|
What next?, or replace with stronger hatch. |
|
|
|
| 3 |
Foresail clew attachment |
12/11/07 |
|
Replace wire strop or fit shackles |
|
|
|
| 3 |
Primary winches |
12/11/07 |
|
Overhaul (badly corroded), see if ratio can be changed. Consider replacement? |
|
|
|
| 3 |
Re-do engine installation |
12/11/07 |
|
Soundproof, fireproof (MCA requirement) Better electrics (New engine?) |
|
|
|
| 3 |
Repairs to steel frame forward |
12/11/07 |
|
Improve Are there any other steel frame improvements required? |
|
|
|
| 3 |
Spinnaker track |
12/11/07 |
01/04/08 |
Repaired but consider replacement with SS. |
|
|
|
| 3 |
Throttle/gear control |
12/11/07 |
23/03/08 |
Replaced with new. Neutral indicator to be wired up. |
|
|
|
| 3 |
Mooring warps |
01/10/08 |
|
Replace badly worn and shortened items with new set |
|
|
|
| 3 |
Boathook provision/retention |
12/11/07 |
|
Decent quality boathooks with positive retention (having lost 2 last year and 1 this!) |
DEG |
|
|
| |
|
|
|
|
|
|
|
| 4 |
Scollop bunk sides |
01/12/08 |
|
To ease access. Lee cloths needed? |
|
|
|
| 4 |
Extra cleat(s)? |
12/11/07 |
|
Forward of sampson post? Anywhere else? |
|
|
|
| 4 |
Holding tank? |
12/11/07 |
|
Probably be a requirement here soon. Already is in many places |
|
|
|
| 4 |
Rev counter at helm/other controls? |
12/11/07 |
|
Checked suitability of alternator (Obsolete!). Engine start? Eng.Alarm. Electric horn? |
|
|
|
| 4 |
Tank gauges? |
12/11/07 |
|
Investigate available solutions |
DEG |
|
|
| 4 |
Straighten or replace anchor |
01/08/08 |
|
Consider change to bow stowing type. |
|
|
|
| |
|
|
|
|
|
|
|
| 5 |
Chartplotter/autopilot/upgrade radar? |
12/11/07 |
|
Consider also Compass stabilisation of Radar. Hi Def/ New Tech. Radar coming? |
|
|
|
| 5 |
Personnal stowage by bunks |
01/08/08 |
|
For valuables, phones, watches etc. |
|
|
|
|
|
|
|
|
|
|
£2,620 |
|
|
|
|
|
|
Contingency |
£980 |
|
|
|
|
|
TOTAL BUDGET |
£3,600 |
|
|
|
|
|
|
|
|
|
RECENTLY COMPLETED JOBS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Jib sheet lead blocks |
12/11/07 |
|
COMPLETED |
|
|
|
| 2 |
No.4 "Storm" Jib |
12/11/08 |
|
Repair or replace. Head torn away. Unsatisfactory design.- COMPLETED |
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Priority |
|
|
Characteristics |
|
|
|
| |
|
|
|
|
|
|
|
| |
1)Immediate Work |
|
|
|
|
|
|
| |
1a) Winter Programme |
|
|
Must be done before launch, for MCA etc |
|
|
|
| |
1b) In Commission |
|
|
Must be done before putting to sea, inluding all safety critical work |
|
|
|
| |
2) Necessary Work |
|
|
Work to be done as soon as possible, or as resources are available |
|
|
|
| |
3) Improvements |
|
|
Preservative or Remedial work, as resources permit |
|
|
|
| |
4) Minor Improvements |
|
|
Improvements, or trial of ideas (reversible) |
|
|
|
| |
5) Suggestions |
|
|
Proposals for wider consideration, not for implementation without feedback |
|
|
|
| |
1 to 4 to be agreed by Preservation Secretary/ Technical Officer |
|
|
| |
|
|